owner
City of Fort Worth
estimated completion date
completion date
August 2021
scope
Construction of New Chlorine Storage Building including three demolition the existing chlorine storage tanks and replacing with 25-ton chlorine storage tanks, new chlorine evaporators, piping and chlorine scrubber system and duct. Improvements also included replacing two existing 25-ton sulfur dioxide storage tanks and associated piping.
contract price
$8,573,000.00