Southwest Pump Station and Storage Facility

/
/
Southwest Pump Station and Storage Facility

Southwest Pump Station and Storage Facility

Owner

UTRWD

Estimated Completion Date

Completion Date

December 2025

Scope

Construction of a 25 mgd treated water pump station, two 5 million gallon Type III groundwater storage tanks, a hydropneumatic surge tank system, external emergency generators, and related piping, valves, vaults, drainage, access roadways, and site civil works. The existing booster station will remain in service and be protected during the construction of the permanent pump station.

Contract Price

$35,857,000.00