Northside PS and Eastside PS No.2 Electrical Rehabilitation

/
/
Northside PS and Eastside PS No.2 Electrical Rehabilitation

Northside PS and Eastside PS No.2 Electrical Rehabilitation

Owner

City of Richardson

Estimated Completion Date

Completion Date

December 2022

Scope

Replace generator, motor control center and electrical equipment at existing pump stations. Install new pump and associated piping at the Eastside PS.

Contract Price

$7,485,000.00