Wilson Creek Lift Station Improvements

/
/
Wilson Creek Lift Station Improvements

Wilson Creek Lift Station Improvements

Owner

NTMWD

Estimated Completion Date

Completion Date

March 2022

Scope

Install two new 500hp vertical centrifugal pumps with new suction and discharge pipe in existing lift station. Install access platforms for all pumps and construct second discharge header with new isolation valves. Upsize existing influent pipeline with new 60” FRP including Junction Box penetrations.

Contract Price

$4,474,000.00